March 23-24,
2000
ITEM 106-1004-R0300������ Revised
Project Authority, Center For Student Success, Series E 1998 Facilities
Improvement And Refunding Revenue Bonds; The University Of Montana - Missoula
THAT:����������������������������������� The Board of
Regents of the Montana University System authorizes The University of Montana
to increase the project authority for Center for Student Success at The
University of Montana from $2,000,000 to $2,100,000.
EXPLANATION:����� ����������� On May 21,
1998, the Board of Regents approved a Center for Student Success as a project
funded by the Series E 1998 revenue bonds.�
The increase of $100,000 is due to 12% construction inflation increase
on bids received March 7, 2000.��
Auxiliary funds will be available for the increase in the project budget
for the Center for Student Success.